Summary

A contractor who abandons the works, or refuses to complete them, ordinarily commits a repudiatory breach. The employer (in a building contract, the owner who engaged the contractor) may terminate the contract and engage another contractor to complete the works. It may then recover the amount by which the total cost of completing and correcting the works, including sums already paid to the original contractor, exceeds the contract price, together with other foreseeable losses. The employer's liability to pay for the work already done depends on the structure of the contract. Where the employer prevented completion, the position may be reversed.

Last reviewed 22 September 2026

Payment for incomplete work. The position depends on the nature of the contractor's obligation:

  • An entire obligation. Where a single price is payable only upon completion of the whole of the works, a contractor who performs only part of the obligation can recover nothing for the work done.
  • Substantial performance. Where the works have been substantially completed, but with defects or omissions, the employer must pay the contract price, less the cost of remedying the defects.
  • Acceptance of partial performance. Where the works have been left incomplete, the contractor is entitled to payment for the part performed only if the employer had a genuine choice whether to accept the partial performance, and elected to do so. An employer who completes works on its own land because it has no practical alternative is not taken to have accepted the partial performance.
  • Stage payments. Building contracts commonly provide for payment by stages. The same principles are then applied to each stage.

Prevention of performance. Where the employer has prevented the contractor from completing the works, for example by excluding the contractor from the site while the contract subsists, the rules set out above do not protect the employer. The contractor may claim damages, or payment on a quantum meruit, that is, the reasonable value of the work done.

The employer's remedies. The abandonment of the works, or their performance so defectively as to defeat the purpose of the contract, is a repudiatory breach. The construction of a dwelling house unfit for habitation is an example. The employer may accept the repudiation, thereby terminating the contract, and claim damages. Those damages ordinarily comprise the amount by which the total cost of completing and correcting the works, including sums already paid, exceeds the original contract price, together with losses caused by the delay. The employer must take reasonable steps to mitigate those losses. Work performed under a contract for services must be carried out with reasonable care and skill. Where a dwelling house is left uninhabitable, damages may also be awarded for the distress resulting from the physical inconvenience.

Practical implications

Where a contractor completes only a portion of the works and then abandons them, that will ordinarily constitute partial rather than substantial performance. If the price was payable only on completion of the whole, the contractor may be entitled to nothing for the work done. In that event, the employer pays only the replacement contractor. It has a claim against the original contractor only if the total cost of completion exceeds the original contract price. An employer who elects to use materials left on the site by the original contractor must pay for them.

Where the employer paid an advance and the contractor failed to perform the corresponding work, the sum paid for work not done forms part of the employer's claim.

Where a contractor declines to complete the works unless additional payment is made, the employer's agreement to pay may be liable to be set aside for economic duress. See Can a contract be varied after it has been signed?

Where the works are complete but defective, the employer must pay the price, less the cost of remedying the defects.

The steel frame of an unfinished building against a dusk sky, a crane above — a contractor who did not finish the job
The works. As they stood when the contractor left.

Before any other contractor enters the site, the employer should record the state of the works fully. The record should include dated photographs and video recordings, a schedule of the work completed and outstanding, and, preferably, an independent report from an engineer or quantity surveyor. That record will be the principal evidence in support of any claim.

The employer should serve written notice on the contractor, identifying the outstanding work and requiring its completion within a reasonable time. Where the contract prescribes a notice procedure or a period within which the breach may be remedied, that procedure should be followed.

If the contractor fails to return, the employer should notify the contractor in writing that it accepts the repudiation and treats the contract as terminated. That acceptance must be clear and communicated.

The employer should obtain competitive quotations from other contractors, act reasonably in selecting one, and retain all receipts.

The employer should not exclude the contractor from the site, or withhold payment for a properly completed stage, while the contract subsists. To do so may place the employer in breach.

Claims not exceeding TT$50,000 may be brought in the Petty Civil Court. In most cases proceedings must be commenced within four years of the breach, which in cases of abandonment ordinarily means the date on which the contractor abandoned the works.

In future contracts, stage payments should be linked to defined milestones. A retention should be held until defects have been remedied, and the basis on which variations will be valued should be agreed in writing.

Important notice. This commentary is a general statement of the law of the Republic of Trinidad and Tobago and is provided for information purposes only. It does not constitute legal advice, and it is not to be relied upon as legal advice or as a complete or current statement of the law. The law may have changed since the date of last review. Readers should verify all information for themselves, including the current text of any legislation referred to, and should obtain legal advice on their particular circumstances before acting, or refraining from acting, on anything in this commentary. Reading this commentary does not create an attorney-client relationship, and no responsibility is accepted for any loss arising from reliance on it. Any decision of a court referred to in this commentary is cited for the principle it states; similar results cannot be guaranteed, and a decision may be subject to appeal or change.

Tell me what has happened.

A few sentences is enough to know whether you have a matter and what it would take.

Make an enquiry Call +1 (868) 338-8895 WhatsApp